Published at : 04 Apr 2023
Volume : IJtech
Vol 14, No 2 (2023)
DOI : https://doi.org/10.14716/ijtech.v14i2.5441
Dewi Permatasari | 1. Departement of Chemical Engineering, Faculty of Engineering, Universitas Indonesia, Kampus UI Depok 16424, Indonesia, 2. Special Task Force for Upstream Oil and Gas Business Activities Republic of |
Fajril Ambia | 1. Special Task Force for Upstream Oil and Gas Business Activities Republic of Indonesia, Wisma Mulia 23 Fl, Jl. Gatot Subroto Kav. 42, Jakarta Selatan, 12710, Indonesia 2. Departement of Petrole |
Eny Kusrini | Departement of Chemical Engineering, Faculty of Engineering, Universitas Indonesia, Kampus UI Depok 16424, Indonesia |
Muhammad Zulkarnain | Fakulti Kejuruteraan Mekanikal dan Pembuatan, Universiti Teknikal Malaysia Melaka (UTeM), Melaka, 75450, Malaysia |
The objective of this study is to
evaluate the comparison of economic incentives from the aspect of production
sharing contract gross split, and taxation, especially to determine the balance
of incentives that the government can provide either in taxation or additional
discretion splits to contractors in the Alfa working area, which is an oil and
gas operational work area located in Kalimantan. The method used in this study
is a quantitative method, by performing calculations using a gross split profit
sharing scheme to observe the economic comparison of Alfa working area without
discretion, with additional discretion and a combination of tax percentages,
with various combinations, it provides 25 (twenty-five) scenarios for economic
calculations to the Alfa working area. Based on the economic calculation in
Alfa's work area, the profitability index (PI) value is 1.09, where this value
shows the minimum economic value of the contractor. Based on these scenarios,
an economic analysis was obtained with a combination of indirect tax 0-100% and
additional discretion split of 0-100%. According to the study's results,
if the additional discretion incentive was less than 50%, the contractor's NPV
value was negative. On the other hand, 75% discretion was given with indirect
tax between 0-50%, and 100% discretion was offered. Through scenario simulation
calculation with a PI target of 1.09, the optimum result was obtained with a
balanced incentive amount at 50% indirect tax and an additional 92% split
discretion.
Discretion; Gross split; Incentives; Indirect tax; Profitability index
Indonesia’s upstream oil and gas
industry is still one of the drivers of the national economy. Oil and gas have
an important role in modern industry, and the demand for oil and gas is closely
related to economic development (Cheng et
al., 2018). Indonesia’s
oil reserves and declining oil production is the focus of the Indonesian
government, which aims to quickly change and accelerate the use of a mixed-energy
policy
(Bawono and Kusrini, 2017). Therefore the
government continues to strive to create an attractive investment climate to
achieve the petroleum production target of 1 million barrels per day and 12 billion cubic feet per day of natural gas (BSCFD) by 2030.
Investors say that oil and gas sector investment
in Indonesia is less attractive. Some publications such as IHS Markit, Wood
Mackenzie, Fraser, and others mention that Indonesia's upstream fiscal
attractiveness rating is relatively low compared to other countries (BUMI, 2021). Indonesia is currently making advances related to the
investment climate in the field of oil and gas, where other countries are also
increasing their attractiveness, Radical investment climate improvements can help to attract oil and gas investors.
To achieve the oil and gas production
target by 2030, all parties need joint efforts. Currently, investors are given
the option to choose the form of the production sharing contract (PSC),
including gross split PSC or cost recovery PSC. There are several incentives
provided by the government, in the Cost recovery Production Sharing Contract
(PSC), the government provides DMO (Domestic Market Obligation) Holiday
rewards, Investment credit, and accelerated depreciation. In the gross split
PSC, the government provides an adjustment to the number of profit sharing,
incentives for the use of state property based on field economic
considerations, exemptions from VAT related to the import and delivery of
certain strategic taxable goods (including LNG), and elimination of the
provision on utilization fees for exterminated state-owned goods
Production sharing contracts in
Indonesia continue to develop according to regulatory changes and the times,
Indonesia has implemented the PSC cost recovery system since 1965 and has
passed through three generations. Since 2017 the government has issued a new
model of the PSC
scheme through Ministerial Regulation No. 8/2017 about Gross Split Production
Sharing Contracts. Since the implementation of this gross split scheme, 16 oil
and gas areas have used the system (Directorate
General of Oil and Gas, 2018). In the gross split scheme, this cost recovery
component is eliminated and secure government revenue (Daniel, 2017), because the split calculation
scheme between the government and the contractor is determined at first (base split),
there are also variable and progressive components and additional components
for contractor revenue sharing, the discretion of the Minister of Energy and
Mineral Resources to improve the economic level of upstream oil and gas
projects. With this discretion, the policy will encourage contractors to drill
more wells. So that the potential of finding new oil reserves will be higher,
which benefits contractors and the government without changing the oil split in
government regulations (Giranza and Bergmann,
2018). Gross split
PSC has similar characteristics to a royalty scheme, which has been successful
elsewhere in the world (Roach and Dunstan, 2018).
Several
researchers have also conducted many studies by comparing PSC Cost recovery and
PSC gross split. Research conducted by Buhori, Rokhim, and Wibowo (2018) shows that PSC cost recovery is more attractive to contractors, In other
research, the results show that this gross split system provides higher cash
flow results for contractors (Jumiati and Sismartono, 2018). An interesting research result was reported by Daniel
(2017), which showed that using the gross
split PSC system would be better without indirect tax. This research was conducted in the Alfa
working area. The Alfa working area received an extension production sharing
contract gross split scheme, the minimum economic indicator that must be achieved
by the contractor is from the value of profitability index is 1.09. The use of
this profitability index indicator is due to the very volatile cash flow
conditions from Alfa working area is always positive so the IRR value is
inaccurate. The Novelty of this paper is to find a
balance of the number of incentives that can divide between taxation and
discretion.
Economic calculations Alfa Working
area uses the Gross Split PSC scheme (Regulation
MEMR No.8, 2017). Table 1, details the gross split
PSC regulates.
The split on this gross split can be
adjusted based on 13 (thirteen) components consisting of 10 (ten) variable
components and 3 (three) progressive components (Regulation MEMR No.8,
2017), this component can be seen in Table
1. Based on the Minister of Energy and Mineral Resources Regulation No.
52/2017, in the economic calculation of the Gross Split PSC in a working area,
the Minister of Energy and Mineral Resources and the Minister of Finance can
provide incentive approval by adding a percentage of split to the contractor.
2.1.
Project Economy
The
decision-making process to determine the value of a long-term investment in a
project requires a techno-economic analysis and should be based on the maximum
return on equity of the investment (Wicaksono,
Arshad, and Sihombing, 2018). This study uses NPV, PI, and POT to determine the economics
of a project.
2.1.1. Net Present Value (NPV) is the discrepancy between the value
of cash inflows and the value of cash outflows for a period. NPV is usually
used as a capital allocation to analyze the benefits of a project to execute.
In addition, NPV is a direct measure of profitability and provides an overview
of how the contractor's cash flow will be affected by each project (Sajjad et al., 2021). Generally, a positive NPV value
will be profitable, while projects with a negative NPV value will result in
losses (Peterson
and Fabozzi, 2002). NPV
can be calculated using the formula 1 below:
Where: N = Number of periods, t = time of cash flow being measured, I = cost of capital, and Rt = cash flow at time t.
2.1.2. Profitability Index This method calculates the comparison
between the value of net cash flows that will come with the value of the
current investment. The
profitability index can be calculated using formula 2 below:
Where:
CF=Annual cash inflow, IO=Total investment, n=project age, and k=capital
interest rate. The Profitability Index must be
greater than one to be considered feasible. The larger the profitability index,
the more feasible the investment (Peterson and Fabozzi, 2002).
2.1.3. Pay Out Time
(POT) or payback period is the time required to recover the initial cost of a
project. This POT is a parameter that indicates the year in which the
Cumulative Cash Flow is equal to 0 (Pramadika and Satiyawara, 2018). POT can be calculated using the formula 3 below:
Where: IO=Initial investment and
CF=Cash inflow
Based on research conducted by (Lyukevich et al., 2020), evaluating the project’s economic risk can use an
algorithm method that is faster with accurate results. This is very important
because the calculation of techno-economic analysis, evaluation of economic
risk is needed to assess risk factors in developing a project. In addition, mitigation
can be made from the risks that have been determined so that the project
implementation is under the plan.
2.2.
Executive summary of Alfa working
area
2.3.
Scenario for calculating the
economics of incentives and taxation
Figure
2 Scenario calculating the
economics of incentives and taxation
The percentage of discretion used is the
greater percentage split obtained from the results of the economic calculation
of the Alfa working area, and for percentage indirect tax is the percentage of
VAT dan LBT. Tax revenue is an important source for sustainable development,
which increases the country's ability to generate its tax revenue (Victorova
et al., 2020). However, to improve the oil
and gas investment climate and contractors can develop alfa working areas, then
the provision of tax incentives is necessary. It follows that if there are no
incentives, the Alfa working area is not developed, and of course, the
government will not receive revenue from this oil and gas sector. Besides, the 25 scenarios
above, this study also simulates calculation scenarios with a target PI of 1.09
and using an indirect tax 0-100%, to find the optimum value of discretion.
3.1. Fiscal terms for
the Alfa working area
Before running economic calculations, it is necessary to determine the distribution of split for the Alfa working area between the government and the contractor formerly using the gross split PSC scheme, according to the MEMR Regulation. Details of the base split based on a base split contractor in Table 1 for oil 43% and gas 48%, variable component, and progressive split based on the condition for the Alfa working area, as shown in Table 2.
Table 2 Fiscal
terms Alfa working area
Component Splits |
Status |
Contractor Split | |
Gas |
Oil | ||
I. Base
Split |
48% |
43% | |
II.
Variable Split | |||
Block
Status |
No POD |
0% |
0% |
Field
location |
Onshore |
0% |
0% |
Reservoir
depth (m) |
>
2500 |
1% |
1% |
Infrastructure |
Well
Developed |
0% |
0% |
Reservoir
Condition |
Conventional |
0% |
0% |
CO2
(%) |
40 <
x < 60 |
2% |
2% |
H2S
(ppm) |
< 100 |
0% |
0% |
Specific
Gravity of oil (API) |
>25 |
0% |
0% |
Local
Content (%) |
50 <
x < 70 |
3% |
3% |
Production
Phase |
Primary |
0% |
0% |
III.
Progressive Split |
|
|
|
Cumulative
production |
<30
MMBOE |
10% |
10% |
Oil/gas
price |
US$/bbl.
US$/MMBtu |
5% |
12% |
Total
contractor Split |
69% |
71% | |
Government
split |
31% |
29% |
Based on
the determination of the alfa working area split, the total results for the
contractor split for gas are 69% and for oil 71%, while the revenue sharing for
the government is 31% for oil and 29% for gas.
3.2.
Alfa working area development costs
Calculating development costs in the Alfa working area
requires data and estimates of capital expenditure costs (CAPEX), and operation
and maintenance costs (OPEX). In the gross
split PSC, the contractor must be as efficient as possible to execute activities
to improve the contractor’s profits. Therefore, CAPEX and OPEX efficiency are
needed, one of which is optimizing development drilling activities. In drilling
activities, it is necessary to formulate the best and optimal drilling fluid to
get the minimum cost (Kusrini et al., 2018; Kusrini et al., 2020).
This
capital expenditure cost (CAPEX) includes drilling costs, facilities, and costs
for G&G Study and seismic, so the total cost of CAPEX is MMUS$ 4,490.8.
This cost needs to execute all the long-term plan work programs in the Alfa
working area, with detailed
annual costs, as
shown in Figure 3.
3.3. Economy Alfa
working area
From the results of economic
calculations using the fiscal term of Alfa working area where the number of
splits has been determined, the contractor's NPV is positive, with discretion
26%, the value of the profitability index (PI) is 1.09, meaning the PI value
more than one which is the minimum value for the contractor to be able to
develop the working area and pay out time is 8 years. From this calculation,
revenue from contractors is MMUS$ 647, and government revenue is MMUS$ 2,899,
as shown in Table 3.
Table 3 Alfa working area economic calculation
Parameter |
Unit |
Fiscal Term Alfa Working Area |
Contractor gas split |
% |
69% |
Contractor oil split |
% |
71% |
Discretion |
% |
26% |
WAP Gas |
S$/MMBtu |
6 |
WAP Oil |
US$/bbl |
59 |
Gross Revenue |
MMUS$ |
10,766 |
Total CAPEX |
MMUS$ |
4,491 |
Total OPEX |
MMUS$ |
3,941 |
Contractor Profitability: | ||
Contractor Net Operating Profit |
MMUS$ |
647 |
(% Gross Revenue) |
6.68% | |
Total Contractor Net Cash Flow |
MMUS$ |
600.64 |
(% Gross Revenue) |
6.20% | |
Contractor NPV |
MMUS$ |
173 |
Profitability Index Pay Out Time |
Years |
1.09 8.4 |
Government Profitability: | ||
Government Take |
MMUS$ |
1,632 |
(% Gross Revenue) |
15% | |
Indirect Tax (VAT, LBT &
Asset Lease) |
MMUS$ |
1,268 |
(% Gross Rev) |
12% | |
Government Take includes Ind Tax |
MMUS$ |
2,899 |
(% Gross Revenue) |
|
27% |
3.4. Calculation of
Profitability Index from 2017-2020 POD Data with Economic Data of Alfa Working
Area
Figure
5 Comparison of PI Data POD 2017 – 2020 with PI Alfa working area
Based on the POD data shows that the
average PI from POD data is 1.55, which means that the results for the economic
calculation of the Alfa working area, where the PI is 1.09, results in
reasonable incentives for the Alfa working area. However, it is below the
average value when compared to the data for each PI POD, the PI value of 1.09,
according to the contractor, is sufficient to develop the Alfa working area.
However, based on the discretion
previously given by the government, the percentage is currently very high.
Therefore, the government wishes to see the discretion value lowered to below
26%. So, a re-evaluation is carried out
regarding the additional amount of the split given. So that in this study an
analysis of the number of incentives provided is not only from the portion of
the Ministry of Energy and Mineral Resources but also from tax, along with
indirect tax exemptions (VAT and LBT), which includes a combination scenario of
a predetermined percentage that has been set upon in the beginning.
3.5. Economic calculation with discretion and
taxation scenario
From the results of the economic calculations of 25 scenarios, it will get the profitability index and NPV value, as shown in Figures 6 and 7. Based on the calculation using formula 1, results in 25 (twenty-five) economic scenarios. Based on Figure 6, the contractor's NPV is negative if discretion is below 75%.
The economic viability of a project other than the NPV value can also be seen from the PI value using formula 2. The PI value is below one if the discretion is below 75%. The PI value in Figure 7 will exceed the minimum value of 1.09 if the contractor gets a tax incentive of 0-75%. At a later stage for pay out time (POT) which was calculated using Formula 3, if NPV is negative, POT is zero. If a value of 75% discretion applies, then the POT is 8 to 18 years.
Figure 7 Comparison of profitability Index of 25 economic
scenarios
For the balance
of the incentive portion between the additional split discretion given by the
Ministry of Energy and Mineral Resources and the indirect tax incentive
provided by the ministry of finance, a calculation simulation with a target PI
value of 1.09, as shown in Table 4.
Table 4 Summary of calculation simulation scenario
Parameter |
Unit |
Indirect Tax: Discretion | |||
0%: 85% |
25%:88% |
50%:92% |
75%:96% | ||
Gross Revenue |
MUS$ |
10,766 |
10,766 |
10,766 |
10,766 |
Total CAPEX |
MMUS$ |
4,491 |
4,491 |
4,491 |
4,491 |
Total OPEX |
MMUS$ |
3,514 |
3,621 |
3,727 |
3,834 |
Contractor Profitability: | |||||
Contractor Net Operating Profit |
MMUS$ |
643 |
643 |
642 |
646 |
(% Gross Rev) |
6.64% |
6.64% |
6.63% |
6.67% | |
Total Contractor Net Cash Flow |
MMUS$ |
606 |
604 |
600 |
602 |
(% Gross Rev) |
6.26% |
6.23% |
6.19% |
6.21% | |
Contractor NPV |
MMUS$ |
173.11 |
172.82 |
172 |
173.44 |
Profitability Index Pay Out Time |
% Years |
8.24 |
1.09 8.26 |
1.09 8.27 |
1.09 8.28 |
Government Profitability: | |||||
Government Take |
MMUS$ |
2,057 |
1,952 |
1,848 |
1,738 |
(% Gross Rev) |
19.11% |
18.13% |
17.17% |
16.15% | |
Indirect Tax (VAT, LBT & Asset Lease) |
MMUS$ |
262 |
513 |
765 |
1,016 |
(% Gross Rev) |
2.43% |
4.77% |
7.10% |
9.44% | |
Gov. Take includes Indirect Tax |
MMUS$ |
2,319 |
2,465 |
2,613 |
2,754 |
(% Gross Rev) |
|
21.54% |
22.90% |
24.27% |
25.59% |
Based on the calculation of the simulation scenario with a
target of 1.09, the results indicate that there are two comparisons of indirect
tax and discretion with large government revenues, in a ratio of 50%:92% and
75%:96%. At a ratio of 75%:96%, the discretion value is 24.9%, where this value
is still close to the initial discretion value of 26%. Thus, the government
wants to calculate the economics of the Alfa working area to achieve a balance
between the number of taxes and discretion. The optimum result is in a ratio of
50%:92%, with a discretion of 23.9%. Similar to the results of research conducted by Daniel (2017), it is emphasized that a gross split PSC is more
attractive than cost recovery PSC if there is no indirect tax, but PP 79/2010
has regulated indirect taxes. The Government's effort in the Alfa working area
by evaluating the balance between tax and discretion is that contractors get
appropriate incentives to continue the development of this work area.
The economic
analysis of the Alfa working area uses the gross split PSC with an additional
split discretion of 26%, the PI value is 1.09 which is the contractor's minimum
economic value. From the approval of the previous economic calculation of the
development of the working area or field, the discretion value of 26% can be
optimized. The results of the optimization calculation for the government
include an indirect tax of MMUS$ 2,613. Based on economic calculations in the
Alfa working area with various scenarios, it can be resumed that with a tax
incentive of 0-100%, the additional discretion split cannot be below 20%. From the evaluation results in the Alfa
working area, it can be seen that consolidation is needed between the Ministry of Finance and the Ministry
of Energy and Mineral Resources to ensure oil and gas incentives for contractors. In this study, the tax incentives used in the scenario
are only limited to VAT and LBT. Suggestions for further research can be an
assessment of other incentives that can be provided by the government such as
the exemption from the use of state property, exemptions from import duties for
goods used for petroleum operation purposes, accelerated depreciation, and
other incentives. This research can be used as a reference to the government
for calculating the balance of incentives in the Alfa working area to obtain
optimum results.
Dr. Eny Kusrini is thankful to Kemendikbudristek for
Penelitian Dasar Unggulan Perguruan Tinggi (PDUPT) Grant No.: NKB-995/UN2.RST/HKP.05.00/2022, and
special task force for Upstream Oil and Gas Business Activities Republic of
Indonesia for the financial support for this work. Authors also thank to Prof. Lee D. Wilson
from Department of Chemistry, University of Saskatchewan, Canada for the
correction on some part of this paper.
Filename | Description |
---|---|
R3-CE-5441-20220203154300.docx | Supplementary CAPEX and OPEX |
R3-CE-5441-20220203154323.docx | Supplementary Oil and Gas Production |
Bawono, A.A., Kusrini, E., 2017. The impacts of financing
investment scenario on piped-natural gas prices (GPs) For Households in
Indonesia. International Journal of Technology, Volume 8(8), 1402–1413
Buhori, A., Rokhim, R., Wibowo, B., 2018. Perbandingan keekonomian antara
skema kontrak bagi hasil cost recovery dengan skema gross split (Economic
comparison between the cost recovery production sharing contract scheme and the
gross split scheme). Master's Thesis, Graduate Program, Universitas Indonesia, Indonesia
BUMI, 2021. Umpan
bagus dorong eksplorasi masif (Good bait encourage massive exploration). Buletin
SKKMigas (Deliverability Not Availability). Jakarta:
Indonesia
Cheng, C., Wang, Z., Wang, J., Liu, M.,Ren, X., 2018. Domestic oil and gas or imported
oil and gas – an energy return on investment perspective. Resources,
Conservation & Recycling, Volume 136, pp. 63–76
Daniel, H., 2017. Indonesian milestone in
production-sharing contract in perspective of government take, contractor take,
cost recovery, and production target. Society of Petroleum Engineers
(SPE-187008-MS). Jakarta: SPE International.
Directorate General of Oil and Gas, 2018. Gross split answers doubts. Jurnal
Migas, pp. 28–29. Available online
at https://migas.esdm.go.id/uploads/perpustakaan/majalah
/Buletin-Migas-Edisi-1.pdf, Accessed on September 22, 2021
Giranza, M.J., Bergmann, E.A., 2018. Indonesia’s new gross split PSC:
is it more superior than the previous standard PSC? Journal of Economics,
Business and Management, Volume 6(2), pp. 51–55
Jumiati, W., Sismartono, D., 2018. Tantangan keekonomian kontrak
bagi hasil gross split dan cost recovery: studi kasus lapangan gas offshore di
sumatera bagian utara (Economic challenges of gross split psc and cost
recovery:a case study of offshore gas fields in northern sumatra). Lembaran
Publikasi Minyak dan Gas Bumi, Volume 53(2), pp. 4–5
Kusrini, E., Oktavianto, F., Usman, A., Mawarni, D.P., 2020. Synthesis, characterization, and
performance of graphene oxide and phosphorylated graphene oxide as additive in
water-based drilling fluids. Applied Surface Science, Volume 506, p.
145005
Kusrini, E., Suseno, B., Khalil, M., Nasruddin,
Usman, A., 2018. Study of the use of nanomaterials as drilling mud additives. In: E3S Web of Conferences, Volume 67, p. 02007
Lyukevich, I., Agranov, A., Lvova, N., Guzikova, L., 2020. Digital experience: how to find a
tool for evaluating business economic risk. International Journal of
Technology, Volume 11(6), pp. 1244–1254
Peterson, P.P., Fabozzi, F.J., 2002. Capital budgeting: Theory and practice. Canada: John Wiley & Sons, Inc
Pramadika, H., Satiyawara, B., 2018. Pengaruh harga gas dan komponen
variable terhadap keuntungan kontraktor pada gross split (Effect of gas prices
and variable components on contractor profits on gross split). Jurnal Petro,
Volume 7(3), pp. 113–117
Regulation MEMR No.8, 2017. Gross split production sharing
contract. Jakarta: Ministry of Energy and Mineral Resources
Roach, B., Dunstan, A., 2018. The Indonesia PSc: the end of an
era. Journal of World Energy Law and Business, Volume 11(2), pp. 116–135
Sajjad, F., Jaenudin, J., Chandra, S., Wirawan, A., Prawesti,
A., Muksin, M. G., Nugroho, W.A.,
Mujib, E.M., Naja, S., 2021. Data-driven multi-asset optimisation
under uncertainty: a case study using the new indonesia's fiscal policy. In: International
Petroleum Technology Conference, Virtual, March 2021
Victorova, N., Rytova, E., Koroleva, L., Pokrovskaia, N., 2020. Determinants of tax capacity for a
territory (The case of the
russian federal districts). International Journal of Technology, Volume 11(6), pp. 1255–1264
Wicaksono, F.D.,
Arshad, Y.B., Sihombing, H., 2019. Monte carlo net present value for
techno-economic analysis of oil and gas production sharing contract. International
Journal of Technology, Volume 10(4), pp. 829–840