Published at : 28 Jun 2023
Volume : IJtech
Vol 14, No 4 (2023)
DOI : https://doi.org/10.14716/ijtech.v14i4.5889
Mulia Orientilize | Civil Engineering Department, Faculty of Engineering, Universitas Indonesia, Kampus UI Depok, 16424, Indonesia |
Widjojo A Prakoso | Civil Engineering Department, Faculty of Engineering, Universitas Indonesia, Kampus UI Depok, 16424, Indonesia |
Yuskar Lase | Civil Engineering Department, Faculty of Engineering, Universitas Indonesia, Kampus UI Depok, 16424, Indonesia |
Sidiq Purnomo | PT Wijaya Karya Beton Tbk, WIKA Tower 1 FL. 2-5, Jl. D.I. Panjaitan Kav. 9-10 Jakarta, 13340, Indonesia |
Ignatius Harry Sumartono | PT Wijaya Karya Beton Tbk, WIKA Tower 1 FL. 2-5, Jl. D.I. Panjaitan Kav. 9-10 Jakarta, 13340, Indonesia |
Winda Agustin | PT Wijaya Karya Beton Tbk, WIKA Tower 1 FL. 2-5, Jl. D.I. Panjaitan Kav. 9-10 Jakarta, 13340, Indonesia |
Experimental study was carried out on three low
confinement spun piles to pile cap connections.
The detail followed the typically fixed connection in Indonesia.
Reinforced concrete was filled to the spun pile to strengthen the connection region,
except SPPC01. Different concrete types were used, shrinkage and non-shrinkage
for SPPC02 and SPPC03, respectively. SPPC02 and SPPC03 could reach the targeted
drift of 3.5% whereas SPPC01 was stopped at a drift of 2.75%. There was no
shear failure detected during the test. The connection behaved as a fixed
connection indicated by the fracture failure of the prestressed bars near the
connection region. Analysis of the test results focused on displacement
ductility. Two definitions of yield and ultimate displacement were employed to
seek the possible ductility values. It varied from 3.05 to 6.04 for SPPC01 and
from 3.01 to 4.95 for SPPC02 and SPPC03. The non-shrinkage concrete did not
affect the strength of the connection but slightly improved the post-peak
behavior. The ductility is 6–12% higher than spun piles with ordinary
concrete. According to the limited
ductility referring to ATC 96, JRA 2002, and AASHTO 2011, all specimens could
achieve target ductility 3. Hence, it can be concluded that the low confinement
spun pile connections performed well in displacement ductility.
Displacement ductility; Experimental study; Low-confinement; Spun pile
The
connection of pile to pile cap in the foundation plays an important role to
transfer the force from the upper to the bottom structure and vice versa. This part is critical since the change of
area, stress, and stiffness occurs suddenly
NEHRP
Several methods have been
proposed to estimate the displacement ductility of the pile. Curvature
ductility is one of the main factors affecting it. To be ductile, the pile section should meet
the required curvature ductility demand
The spun pile is a precast prestressed
pile that is massively used in bridges and wharves. Experimental and numerical
studies of this pile and its connection to the pile cap have been performed by
many researchers. In China, the study
was performed on different connection details
In Indonesia, the spun pile is produced
with a limited amount of transverse reinforcement and below the minimum
requirement in accordance with
Indonesia should move forward to PBD
for the bottom structure since based on the recent seismic risk map, where the
ground acceleration tends to increase
Three
full-scale spun pile connections were tested until failure to evaluate their
seismic performance. To represent the real condition, the pile was picked from
the stocking yard. A length of 220mm was
cut from the middle part which has less confinement according to the research
objective. The spiral pitch is 120mm
where the volumetric ratio is 0,113%.
To clarify the quantity of transverse reinforcement, the amount is
compared to three equations and presented in Table 1. As can be seen, the
equations result in different required quantities. The revised equation
proposed by
Table 1 The requirement of transverse reinforcement
2.1. The Specimens
Figure
1 shows the DED of the specimens. The
450mm in diameter spun pile was chosen with a wall thickness of 80mm. The spun
pile was made of 57Mpa of concrete strength, reinforced by a 10@7.1mm PC bar,
and confined by a spiral of 4mm in diameter. The connection between the spun
pile and the pile cap was designed based on the common practice in Indonesia.
The spun pile was embedded in the pile cap at a depth of 100mm. The required
embedment length of the rebar was 620mm. To reduce the depth of the pile cap,
the length was 500mm straight and the 200mm was bent 30 degrees as shown in
Figure 1. SPPC01 was an empty spun pile, whereas SPPC02 and SPPC03 were filled
with concrete and reinforced by 6D19 as shown in Figure 2.
Figure
1 The connection details (a) SPPC01; (b) SPPC02/3
and (c) the test set-up
SPPC02
represents the typical connection where for ease in construction the concrete
infill was cast together with the pile cap. Additional rebar of 6D19 was added
and embedded into the pile cap to improve the connection strength. Shrinkage of the concrete infill was a
concern and therefore in the preceding research, non-shrink concrete was used
Figure
2 The cross-section of
SPPC01 and SPPC02
The pile cap was cast
by 30Mpa of concrete strength and the actual strength of 28 days age was 34MPa.
Due to the pandemic situation, the experimental test was delayed and the
concrete age of SPPC03 was based on a 56-day test which was 36.5 MPa. The strength
of steel employed in the experiment is presented in Table 1.
2.2. The Test Set-Up
Figure
1 shows the test setup. The specimen was attached to a strong floor and tied
with 10 anchoring bolts. It was loaded vertically as 500kN which was equal to
0.1fc’Ag. A
reverse cyclic lateral load was applied after the vertical force was fully
applied. The horizontal loading
protocol followed the ACI 437-07, where the test was conducted until a targeted
drift of 3.5% was achieved or until the strength of the specimen was dropped by
more than 25%. Seven and two transducers were employed to measure horizontal
and vertical displacement, respectively. The concrete strain gauge was put on
the spun pile and pile cap which was located 100mm from the connection. The strain
of the reinforcement bar was measured through 6 strain gauges which were placed
next to the connection in the loading plane. Meanwhile, four strain gauges were
attached to the prestressed wire at a similar location.
3.1. The Hysteretic Curves
SPPC02 and SPPC03 were tested until they
reached a drift of 3.5% whereas SPPC01 was stopped at a drift of 2.75% since
its strength drop more than 50%. Figure 3 shows the hysteretic curve and the
envelope of all specimens. As can be
seen, the presence of the reinforced concrete infill in SPPC02 and SPPC03
changes the performance of the spun pile connection significantly. It improves
strength and energy absorption. The envelope of SPPC02 and SPPC03 are very closed which
indicates that different concrete type does not affect the strength of the
connection.
3.2. The Crack Pattern
The crack pattern on the spun pile is
shown in Figure 4. There was a slight shear-flexural crack was detected at
several places. The crack initiated from the tensile face and propagated to the
center of the spun pile. The majority of the crack was a result of flexural
failure. The crack propagated until 650mm from the connection region of SPPC02
and almost 800mm of SPPC03. Meanwhile, the last crack of SPPC01 was detected at
depth of 400mm above the connection.
Light
damage was found on the pile cap of SPPC01. Concrete crushing of the pile at
the connection region was observed when drift reach 2%. A similar failure mode occurred on SPPC02 and
SPPC03. The first crack of the spun pile was at a drift of 0.35% and 0.5%. The
pile cap suffered moderate damage where a crack was detected on its surface
with a depth of less than 100mm. It started from the connection region and then
it propagated to a radius of 150 to 180mm from the pile face.
Figure 4 The Crack
Patterns (a)SPPC01, (b) SPPC02, (c) SPPC03
The
prestressed wires of all specimens suffered a fracture. Nine bars of SPPC01 were found fractured and
one was necking. Meanwhile, seven bars
of SPPC02 dan SPPC03 were fractured and one was found necking in SPPC03. The locations were +20-30mm from the
pile cap surface. It indicated that the
anchorage length of the PC wires was sufficient to prevent the slip of the
connection. The amount of reinforcement in the pile cap was also adequate since
the concrete spalling only occurred on the concrete cover.
Figure 5 Determination
of ductilities: a)SPPC01; b)SPPC02; c)SPPC03 and d) the summary of ductility values
3.3. The Ductility
Displacement
ductility is determined as a ratio of ultimate displacement (du) to
yield displacement (dy). For reinforced concrete structures, dy
is not well defined due to the nonlinearity of two materials, i.e., concrete
and steel. The are two common methods to define yield displacement. Firstly, It
is based on an equivalent area of the bilinear elastoplastic curve and it is
constructed where the energy absorption is equal
The
ultimate deformation has several assumptions.
The two most definitions used by a researcher are the displacement
corresponding to the peak load
Figure 6 The
ratio of dissipated energy (Ed) to input energy (Ei): a)SPPC01, b)SPPC02,
c)SPPC03
To
confirm the occurrence of yielding, the dissipated energy was observed. It is
the energy absorbed by the structure during the inelastic stage which is
indicated by the area of the hysteresis curve of each cycle. The input energy
is the area below the force-displacement curve. Figure 6 presents the ratio of
the dissipated energy (Ed) to the input energy (Ei). The significant yield is
shown as the minimum ratio where the amount of dissipated energy starts to
increase rapidly. The data appears scattered for SPPC01 and a drift of 0.35% is
the lowest point before it escalated. The significant yield occurred at a drift
of 0.75% for SPPC02 and SPPC03. The comparisons of possible occurrences of
yielding are presented in Table 4. Dy1
has a closer value to the significant yield than dy2 for
SPPC01. Meanwhile, dy2 estimates the occurrence of significant yield
better than dy1 for SPPC02 and SPPC03.
The
summary of ductility values based on two different yields and ultimate
displacements is presented in Figure 5.
The range of ductility values of SPPC01 is relatively large about 3
scales. Meanwhile, SPPC02 and SPPC03
have ductility from 3.01 to 4.95. Referring to the meaning of ductility as the
capacity of the structure to deform up to the post-peak stage without
significant loss of strength, hence, du2 is the precise definition.
The results are named ductility #3 and #4.
The difference in value is lesser from 0.5 to 1 as follows: 4.98 and
6.04 for SPPC01, 4.07 and 4.68 for SPPC02, and 4.55 to 4.95 for SPPC03. Based
on significant yielding, ductility #5 was determined and the results were 6.10,
3.78, and 3.66 for SPPC01, SPPC02, and SPPC03, respectively. The values are lower than ductility #3 and #4
for SPPC02 and SPPC03.
Table 4 The comparison of possible yield displacement (dy)
Specimens |
dy1 (mm) |
dy2 (mm) |
Significant Yielding
(sy) (mm) |
Ductility #5 (du2/sy) | ||
Push |
Pull |
Push |
Pull | |||
SPPC01 |
6.12 |
-6.67 |
7.59 |
-7.88 |
6.3 (0.35%) |
6.10 |
SPPC02 |
10.83 |
-10.95 |
11.75 |
-13.30 |
13.5 (0.75%) |
3.78 |
SPPC03 |
11.63 |
-8.89 |
12.13 |
-9.96 |
13.5 (0.75%) |
3.66 |
The experimental study showed that the spun pile to pile cap
connections behaved as fixed restrained with no slip detected. The failure mode
was crushing of the concrete and almost all prestressed wires fractured at the
connection region. Flexural crack dominated the crack pattern.
The
displacement at post-peak load with the strength reduction of 15% is
appropriate to determine ultimate displacement du. Meanwhile, the
secant stiffness approach is preferred to define yield displacement dy.
Four variation values of ductility were obtained based on two definitions of du
and dy. The range values are considered large which are 3.05 to 6.04
for SPPC01, 3.09 to 4.95 for SPPC02, and 3.01 to 4.68 for SPPC03. All specimens
could reach the ductility limit, of three, referring to ATC 96 and JRA 2002.
Hence, the low confinement spun pile showed adequate performance.
SPPC01, the empty spun pile, showed
poor energy dissipation than SPPC02 and SPPC03 which reveals from the
cumulative dissipated energy and the wider crack distribution on the spun pile.
Non-shrinkage concrete strength affects the post-peak behavior of SPPC03 where
its strength drops more faintly than SPPC02. It has slightly better
displacement ductility when post-peak is defined as the maximum displacement.
The
research was supported by the Indonesia Ministry of Research and Universitas
Indonesia through Applied Research, contract number NKB-254/UN2.RST/
HKP.05.00/2021 and PT Wijaya Karya Beton, Tbk.
ACI Committee, 2019. ACI 318-19: Building Code Requirements for
Structural Concrete and Commentary. American Concrete Institute: Farmington
Hills, MI, USA AASHTO, 2011. AASHTO Guide Specifications for LRFD Seismic Bridge
Design. AASHTO. 2nd ed Antonius., P., Harprastanti, P., 2019. Experimental Study of the
Flexural Strength and Ductility of Post Burned Steel Fiber RC Beams. International
Journal of Technology, Volume 10(2), pp. 428–437 Bang, J.W., Oh, S.J., Lee, S.S., Kim, Y.Y., 2016. Pile-cap
Connection Behavior Dependent on the Connecting Method between PHC pile and
Footing. Journal of the Korea Institute for Structural Maintenance and
Inspection, Volume 20(3), pp. 25–32 Budek, A., Benzoni, G., 2009. Obtaining Ductile Performance from
Precast, Prestressed Concrete Piles. PCI Journal, Volume 54(3), pp.
64–80 Budek-Schmeisser, A., Benzoni, G., 2008. Rational Seismic Design
of Precast, Prestressed Concrete Piles. PCI Journal, Volume 53(5), pp.
40–53 Chai, Y.H., Hutchinson, T.C., 2002. Flexural Strength and Ductility
of Extended Pile-Shafts. II: Experimental Study. Journal of Structural
Engineering, Volume 128(5), pp. 595–602 Chiou, J.S., Tsai, Y.C., Chen, C.H., 2011. Simple Estimation for
Ductility Capacity of a Fixedhead Pile in Cohesive Soils. Canadian Geotechnical
Journal, Volume 48(10), pp. 1449–1460 Fanous, A., Sritharan, S., Suleiman, M., Huang, J.W., Arulmoli,
A.K., 2010. Minimum Spiral Reinforcement Requirements and Lateral Displacement
Limits for Prestressed Concrete Piles in High Seismic Regions. Reports and
White Papers, pp. 1–164 FEMA P-750, 2009. NEHRP Recommended Seismic Provisions.
Federal Emergency Management Agency Guo, Z., He, W., Bai, X., Chen, Y.F., 2017. Seismic Performance of
Pile-Cap Connections of Prestressed High-Strength Concrete Pile with Different
Details. Structural Engineering International, Volume 27(4), pp. 546–557 Irawan, C., Djamaluddin, R., Raka, I.G.P., Suprobo, P., 2018.
Confinement Behavior of Spun Pile Using Low Amount of Spiral Reinforcement - An
Experimental Study. International Journal on Advanced Science, Engineering
and Information Technology, Volume 8(2), pp. 501–507 Irawan, C., Raka, I.G.P., Djamaluddin, R., Suprobo, P., 2017. Ductility
and SEismic Performance od Spun Pile Under Constant Axial and Reverse Flexural
Loading. International Symposium on Concrete Technology (ISCT 2017), pp.
35–44 Ling, J.H., Lim, Y.T., Jusli, E., 2023. Methods to Determine Ductility of
Structural Members: A Review. Journal of the Civil Engineering Forum, Volume
9(2), pp. 181–194 Pramono, S., Prakoso, W.A., Rohadi, S., Karnawati, D., Permana,
D., Prayitno, B.S., Rudyanto, A., Sadly, M., Sakti, A.P., Octantyo, A.P., 2020.
Investigation of Ground Motion and Local Site Characteristics of the 2018
Lombok Earthquake Sequence. International Journal of Technology.
Volume 11(4), pp. 743–753 Wang, T., Yang, Z., Zhao, H., Wang, W., 2014. Seismic Performance
of Prestressed High Strength Concrete Pile to Pile Cap Connections. Advances
in Structural Engineering, Volume 17(9), pp. 1329–1342 Yang, Z., Li, G., Nan, B., 2020. Study on Seismic Performance of
Improved High-Strength Concrete Pipe-Pile Cap Connection. Advances in
Materials Science and Engineering, Volume 2020, pp. 1–22 Yang, Z., Wang, W., 2016. Experimental and Numerical Investigation
on The Behaviour of Prestressed High Strength Concrete Pile-to-Pile Cap
Connections. KSCE Journal of Civil Engineering, Volume 20(5), 1903–1912
Zhang,
X., Niu, S., Yan, J.B., Zhang, S., 2019. Seismic Behaviour of Prestressed
High-Strength Concrete Piles Under Combined Axial Compression and Cyclic
Horizontal Loads. Advances in Structural Engineering, Volume 22(5), pp.
1089–1105