Published at : 25 Jan 2024
Volume : IJtech
Vol 15, No 1 (2024)
DOI : https://doi.org/10.14716/ijtech.v15i1.5136
Intan Baroroh | Department of Naval Architecture and Ship Building, Marine Science and Technology, Hang Tuah University (UHT), Jalan Arief Rahman Hakim 150 Surabaya, East Java 60111, Indonesia |
Buana Ma’ruf | The National Research and Innovation Agency (BRIN), Jalan Hidro Dinamika, Keputih, Sukolilo, Surabaya. East Java 60111, Indonesia |
Minto Basuki | Department of Marine Engineering Institut Teknologi Adhi Tama Surabaya (ITATS), Jalan Arief Rahman Hakim 100 Surabaya, East Java 60117, Indonesia |
Didik Hardianto | Department of Naval Architecture and Ship Building, Marine Science and Technology, Hang Tuah University (UHT), Jalan Arief Rahman Hakim 150 Surabaya, East Java 60111, Indonesia |
Tri Agung Kristiyono | Department of Naval Architecture and Ship Building, Marine Science and Technology, Hang Tuah University (UHT), Jalan Arief Rahman Hakim 150 Surabaya, East Java 60111, Indonesia |
Implementation of system installation risk
on engine room module aims to anticipate ship production delays. However, in its implementation, there is the
problem of ship delivery delays in various shipbuilding companies. This research will analyze the risk analysis of the
installation of the engine room module system by identifying risk factors and
parameters that affect performance as a hazard identification that has the
potential to cause delivery delays.
The object of the research is the Indonesian Navy's
Auxiliary Hospital Ship, which has 6 zones with a pilot project developed in
zone 2. This includes an engine room that contains important constructions in
the form of a main motor foundation, auxiliary motor, and other machinery,
where the system was integrated.
Moreover, there are some works consisting of
construction, outfitting, and commissioning which are very complicated and
require high accuracy. The aim of the implementation of risk analysis of the installation
system in the engine room’s module is to assess potential risks, the
effect of risk on project delays, and project cost overruns. The research
method uses a Bayesian network because it is able to assess the most potential
risks and predict the possibility of delays at network nodes. The primary risk is associated with electrical
activities, specifically electrical
outfitting on wiring, clamping, and compound sub-components with a probability
of (0.0002560) in the Machinery Outfitting and Electrical Department. This risk stems from
inappropriate steps during drawing revisions, which have the potential to cause
delays in equipment installation, cable material procurement, and the
generation of cable cutting data. Therefore, early coordination with production
planning control, design, and the supply chain is crucial.
Bayesian network; Installation engine room module; Risk analysis
According to the Governing Council of the Indonesia National Ship Owner's Association (DPP INSA), the total ship class acceptance units, based on PT. BKI's report on new buildings from 2009 to 2018, show that the increase in class acceptance reached its peak in 2013. Furthermore, there was a decline from 2014 to 2017, and at the beginning of 2018, there was a growth of 829 units of ships compared to in 2016. This has a positive impact on the growth of national shipyards. Based on shipbuilding data at PT. PAL Indonesia, from 2011 to 2015, the development of shipyards in East Java experienced delays in two ships in the form of a 17.500 LTD tanker, two Tug ships of 2400 HP, and a SSV Philippines Navy ship."In the case of PT. Dumas Tanjung Perak shipyards, there were four shipbuilding delays from 2011 to 2020, including the 3500 DWT Hull No 109 tanker, 3500 DWT Hull No 111 tankers, 60 meters, and Fast Patrol Boat. Whilst PT. Dock and Shipping Surabaya was delayed in the production of Landing Craft Tank ships, Landing Craft Tank 100 TEUS, Tanker 6.500 DWT, and Self-Propelled Barge Cement Carrier.
The condition description of PT. PAL Indonesia, PT. Dumas
Tanjung Perak shipyards and PT. Dock and Shipping Surabaya has suffered
considerably due to a late penalty of delivery. Other losses are also in the
form of loss of trust from the ship owner and the bank as a lender. Besides, it
declines the company's performance. The latest developments in East Java
shipyards are accelerating production with the modular (Zone) system method on
hospital auxiliary ships whose construction plan was carried out on September
16, 2019. It planned handover of September 30, 2021, but there is a setback
until December 8, 2021, because of various obstacles during production,
especially the complex system in zone 2 of the engine room. The
loss of
shipbuilding delays can actually be reduced or anticipated if the risk
management process is implemented and executed properly at the beginning of the
project. The probability of risk can be calculated by various methods,
one of which is the Bayesian network (BN) approach. BN can be used in various
dynamic security and risk analyses due to its flexible structure on the cause of failure and
mutual conditional dependence by performing probability updates. Meanwhile,
quantitative risk analyses, such as Bow-tie, Barrier block diagram, and Petri net,
show an inability to consider conditional dependencies amongst underlying
events Zarei et al. (2017). The Bayesian method has also proven capable of being used
in complex model development Burova et al. (2021) by using a weighting method to evaluate
business economics risk Lyukevich et al. (2020). The advantages and flexibility of the Bayesian network
method are chosen in the risk analysis of the complex system installation of
the engine room zone 2.
Risk
measurement using the AHP (Analytic Hierarchy Process) is also carried out by (Zhong, Lv, and Zhang, 2019; Jia, Zhao, and Zhang,
2013). Moreover, Zhong collects the risk factors that
are potential from company T projects adapted to the Delphi method. After a few
rounds, it got 22 factors of level three from the factors of level 6 is
original. Then, filter 22 factors of level
three to identify TOP 10 factors using the Analytic Hierarchy Process (AHP).
Then, calculate the weights of all factors and get a list of the top 10 critical factors. Likewise, a
market risk mitigation strategy using the FUZZY FMEA method has been carried
out by Rahmatin et al. (2018) in food
companies by increasing promotion strategies,
promotion strategies are used as mitigation aspects. Risk for contractor expectations
versus insurance company policies by Hatmoko, Astuti, and Farania (2021), which causes the
head office to lose insurance claim benefits. Probabilistic Risk Assessment of COVID-19 Patients by Ting, Zakariah, and Yusri (2022) using the Logistic
Regression instrument.
Risk Control Failure of Iron Pipes by Suwandi, Zagloel, and Hidayatno (2021). However, the interactions are not clear and measurements
have not been carried out. While the impact of the risk variable cannot be
seen, its effect on the performance system.
Bayesian Risk Measurement in banking
institutions and the construction industry has been carried out by (Eschmann et al., 2019; Erango and Goshu, 2019; Zhou et al.
2018; Do and Yin, 2018; Fong et al., 2017; Kim et al. 2012;
Kumar, 2010). In addition, Zhou et al. (2018) did a risk assessment
and showed that the Bayesian network method performs risk assessment
effectively and works flexibly with offshore wind power
construction. The results inform risk mitigation measures by identifying risk sources using a Bayesian dynamic model. The measurement of the
risk of the shipbuilding industry with the Bayesian network with a
questionnaire approach has been carried out by Lee,
Park, and Shin (2009). The model developed for each network at its node has
not been analyzed until the risk value (VaR/Value at Risk) is obtained. The
activities carried out are limited n to n relationships, meaning that one
potential risk has an influence on one risk. Then, a risk analysis is carried
out on material components Basuki et al.
(2014). The subcomponents that
are most likely to cause project delays are the hull and engine equipment, so
they become the main priority in the installation of the engine room and its
equipment.
The duration of shipbuilding in the Indonesian Navy's Auxiliary Hospital
shipbuilding zone there are 6 zones. The construction time of the engine room
zone reaches the longest time, which is 76% of the total ship construction
time. The total blocks that make up the engine room zone reach 30% of the
weight of the 6 zones of ship arrangement. It contains complex systems
integrated into the form of main motor foundations, auxiliary motors, and other
machinery, as well as complex construction, outfitting, and commissioning that
require high accuracy. The engine room is the most urgent object of the
research on the W000302 shipbuilding process at PT PAL Indonesia's shipyard.
The
previous studies such as (Ting, Zakariah, and Yusri,
2022; Suwandi, Zagloel, and Hidayatno, 2021; Zhong, Lv, and Zhang, 2019; Basuki et al., 2014; Jia, Zhao, and Zhang, 2013), researchers are still in the stage of risk
identification, they have not thought about how to proceed with the research.
Many studies have shown that the implementation of the Bayesian Network leads
to better results. The purpose of this research is to identify and assess
engine room installation risks of the Navy Auxiliary Hospital shipbuilding by
using Bayesian Network. However, in this study a quantitative measurement of
the risk analysis has been carried out using the Bayesian method in relation to
the risk variable in each activity in each production workshop. This was due to
various constraints during production, especially complex systems in the zone 2
machine room.
The
gaps from previous research include: The use of Bayesian is still rare in the
field of ship production. Research from Basuki et al. (2014) has used Bayesian methods, but what is done is measuring the probability
of shipbuilding globally. However not all modules on the ship have the same
work, so it is less precise or less specific when applied to modules that are
complex in nature with work that requires a large volume of work. In the engine room zone, although it has a
small module form compared to other modules in the ship's body, it is a
specific zone that requires a high level of difficulty and a large volume of
work. This engine room zone absorbs the most cost and the longest time compared
to other parts of the zone on the ship's body. This is what requires a separate
study to measure the probability and impact of the risk evaluation. This is a gap from research studies regarding
engine room installations, so this research is very important to be carried out
in the construction of the Navy Auxiliary Hospital shipbuilding.
The risk measurement with conditional
probabilities in the engine room module installation model using a Bayesian
network. This model is expected to be able to analyze the magnitude of the
dominant factors that affect the delay in the installation of the engine room
zone in ship construction. The findings of risk
priorities at engine room installation points are used as a reference for
mitigation strategies for shipyards in overcoming delays. This research does not end
with Bayesian analysis but must be continued with quantitative impact
measurements. Not only with the solution of the shipyard management policy, but
there should be scientific results based on the calculation of the model formulation.
Daszynska-Zygadlo
(2012) advocates the use of scenario analysis in risk management studies in
future research. Risk evaluation using the scenario analysis approach allows
users to evaluate the impact of risks on the production process and develop strategies
for risk management in future studies.
As given in the
previous section, this study focuses on PT. PAL Indonesia on the
engine room installation of a new building code W000302. It focuses on
assessing the probability of risks that are affecting the engine room
installation activities. Risk identification is carried out on each production
component of the workshop related to engine room installation activities by
identifying all risks of project completion delays. Risk probabilities are
needed to build a Bayesian network that includes the investigation of hazard
correlation based on the number of nodes in the network using a probabilistic
approach Basuki et al. (2014). Bayesian Networks (BN) is a
powerful probabilistic approach often used for reasoning, diagnosis,
prediction, and decision-making under uncertainty. The engine room installation activity has an
impact on the occurrence of risks that are influenced by three kinds of factors
Ben-Asher (2008), namely:
a. Performance factor, which
is a factor that reflects a decrease in performance.
b. Cost factor, which is a
factor that reflects the additional cost.
c. Schedule factor, which is a
factor that reflects the delay in the schedule
Based on the occurrence of the
engine room installation process, there are several potential risks, risk
events, and risk agents. The potential risk is assessed using the Bayes theorem
probability, where there is a partition relationship between the parts that
make up the entire sample space as shown in Figure 1.
Figure 1 Partitions concept for
engine room installation production process
According to Figure 1, A:
Production process of engine room installation; A1: Machinery Outfitting; A2: Electric, Electrical
Outfitting A3: Steel Work; A4: Piping System; A5: Fabrication; A6: Assembly; A7: Erection; A8: Painting and Protection; A9: Outfitting Manufacturing; A10: Accommodation Package in the Engine
Room Area. Ten workshops
associated with codes (A1 to A10) were analyzed by a Bayesian method.
According to Figure 1, it can
be formulated in equation 1-4 for Bayesian solutions as follows: if
is the
partition space of the sample space S and if the partition have probabilities not equal to zero, then the probability is:
The Bayesian Network Model based on the Bayes theorem will be described
in more detail in accordance with the identification of risks in the work of
several workshops related to the production process of engine room
installation, according to Figure 1. Figure 1 explains the installation system
in the engine room has synergy and close interrelationships in it. This system
cannot function properly without mutual support between sub-models in the
engine room installation work. The successful execution of this work requires
full cooperation among these sub-models within the series of engine room
installation systems. The method consists of four stages, including:
· Risk identification on the sub-model in the engine room installation
system is done by collecting risk identification as
information or primary data to be taken in the field in the form of surveys,
interviews, and filling out questionnaires by the shipyard.
· Determine the weighting factor of each ship repair activity. The basis
for the preparation of weighting factors in work activities based on
"Proportional production progress" means that the balance in carrying
out production is divided into several stages of work. The weighting factor is
based on either the volume of block weight or the man-hour budget. The
estimation of man-hours for each activity is based on existing experience and
the level of difficulty. The difficulty factor is obtained from the experience
of the workshop or workers in carrying out the activity process. Essentially, the man-hour budget for each job or activity already takes
into account both the volume and the difficulty factor. The weighting factor
obtained varies depending on the workload in each process.
· After the weighting factors are given to the BN network model, the
calculation of the chances of each activity against the constraining factors
that affect these activities in each workshop begins. The risk opportunities
for each activity are summed up in total, so they become the total risk
opportunities for activities in each workshop. These delay factors will be used as the basis for creating a Bayesian
network involved in the engine room installation.
· Measuring delay factors using Bayesian theory with the latest
measurements, conclusions are drawn from the results of risk analysis in engine
room installation. The analysis of high-risk constraints in delay values serves
as a reference for developing further mitigation strategies.
Results
Based on the occurrence of
the engine room installation process and the results observed during the study
on the production code W000302, the researcher analyzed the results and developed the following model under the
Machinery Outfitting (MO) and Electrical Outfitting (EO) Departments, including
the piping workshop, machinery outfitting, steel work, electrical, electrical
outfitting. Meanwhile, activities under the Hull Outfitting and Accommodation
Outfitting Department include Outfitting Manufacturing workshops, Package
Accommodations in the Engine Room area, and Painting and Protection. In
contrast, the activities are under the Department of Hull Construction. It includes fabrication, assembly, and erection. All of these workshops
had a role in the construction of the W000302 ship engine room system
installation, PT. PAL Indonesia was found to have several potential risks. Researcher apply the concept of
probability and the Bayesian method with the weight of each factor obtained
from historical data records of PT. PAL Indonesia, as shown in Figure 2. The basis for the preparation of weighting
factors in work activities is based on Proportional production progress. The value of the weight of each process is obtained from data collected
by the shipbuilding company. The weight values ??will differ for different
shipbuilding processes and shipbuilding companies. It depends on the ship base
owned by the shipbuilding company. The factor is the target value carried out
by each activity workshop.
Ten related workshops that make up the engine room
installation can be analyzed by using a Bayesian network to get the delay
probability value for each factor. The probability value for each factor is the
multiplication result of 1/10 (since there are ten factors) and the weight of
each factor (derived from historical data, as described earlier). Probability
on Bayesian networks is needed to assess any possible delays in the production
process as the focus of this study.
Figure 2 The weighting of the Bayesian main network model
in the engine room
The risk approach for each activity of the Bayesian network new building
engine room model was calculated using the following formula: Risk =
probability of risk occurrence x consequence of risk occurrence. The delay of
the engine room installation process is obtained from the conditions in the
shipyard. The results of this probability of risk occurrence are the basis for
the variable values of the factors that cause delays in each workshop. The
value of this variable causes the performance value of the workshop to decrease
from the initial planning. The decline in the performance of each workshop
affects production delays that cause delays in production time, financial
losses, and even the most severe contract cancellation. For this reason, it is very
necessary to apply risk evaluation in every shipbuilding project to anticipate
losses early. Bayesian probability in each activity of the Bayesian network new
building engine room model is shown in Table 1.
The
network model under the Department of Machinery Outfitting and Electrical
Outfitting includes the Bayesian network model of Machinery Outfitting, shown
in Figures 3(a), (b), (c), and (d).
Table 1 The probability of the Bayesian network engine room model
Activity |
Factor Weight |
Probability |
Machinery Outfitting (MO) |
0.0188 |
0.0003760 |
Electrical Outfitting (EO) |
0.0075 |
0.0004650 |
Steel Work |
0.0117 |
0.0003900 |
Piping System |
0.0176 |
0.0001340 |
Fabrication |
0.0082 |
0.00020377 |
Assembly |
0,0141 |
0.00035252 |
Erection |
0.0071 |
0.00017721 |
Outfitting Manufacturing |
0.0050 |
0.0000830 |
Accommodation Outfitting |
0.0097 |
0.0001940 |
Painting & Protection |
0.0113 |
0.0003770 |
Total |
0.1100 |
0.0027790 |
Figure 3
Bayesian networks: (a) Machinery outfitting; (b) Electric outfitting; and (c)
Steel Work