Published at : 06 Oct 2021
Volume : IJtech
Vol 12, No 4 (2021)
DOI : https://doi.org/10.14716/ijtech.v12i4.4827
Agus Wibawa | Department of Mechanical Engineering, Institut Teknologi Sepuluh Nopember, Jl.Teknik Kimia Keputih Sukolilo Surabaya 60111, Indonesia |
Djatmiko Ichsani | Department of Mechanical Engineering, Institut Teknologi Sepuluh Nopember, Jl.Teknik Kimia Keputih Sukolilo Surabaya 60111, Indonesia |
Muhammad Nur Yuniarto | Department of Mechanical Engineering, Institut Teknologi Sepuluh Nopember, Jl.Teknik Kimia Keputih Sukolilo Surabaya 60111, Indonesia |
Today,
there is an oversupply of 23.5 GW (47.7%) in the electricity system of
Indonesia. PT.PLN, the state-owned electricity company, needs decision criteria
to decide whether the power plant should be continue operated, rehabilitated or
demolished. Base on the literature review, none of the frameworks in the world
could be used to solve this problem. Therefore, this research proposed a new
method or framework called HOME (Holistic Operation & Maintenance
Excellence). The method has proposed and analysed in this research combines
engineering analysis (efficiency and reliability) and economic analysis, which
are total cost (acquisition cost, fuel cost, operation cost, and maintenance
cost) and revenue. The objective is to define decision criteria to maximize the
profit and minimize the cost has spent by a power plant. The final results are
the decision criteria for a power plant, wheater to continue operated,
rehabilitated, relocated, or demolished. A sub-critical coal power plant, 400
MW, has been selected as a case study. Two scenarios of coals (LRC and HRC) and
CF (79.46% and 60.96%) have been analyzed. Coal variation is used to evaluate
its impact on efficiency and reliability, while CF change would represent the
external and uncontrollable factor that impacts its revenue. The results showed that the thermal
efficiency when using LRC (4,220 kcal/kg) reduced from 36.99% to 35.18%
compared to HRC (4,917 kcal/kg), while the plant availability decreased from 97.93%
to 97.45%. Nonetheless, the annualized profit when using LRC at the CF of
79.46% was 18.31 million USD/year, and it was a preferable option compared to
7.80 million USD/year when using HRC. Furthermore, the CF has
predicted a reduction to 60.96%. In this situation, the power plant was better
rehabilitated or relocated when it used HRC because it needs a minimum CF of
63.83% to get a break-even point (CFBEP). Conversely, the plant
could continue to operate when LRC is used because CFBEP was 50.82%.
Based on the analysis results, HOME is a good approach to determine and aid
decision-making on the strategies required to operate and maintain a power
plant comprehensively through its whole life cycle.
Cost; Efficiency; LCM; Reliability; Revenue
A coal-fired power plant is one of the most common options to meet base-load demand in the electricity system due to mature technology and competitive cost (Barros et al., 2016). It is expected to project relatively 31% of the world power generation by 2040 (IAE, 2017). The disadvantages are its negative impact on the environment, “dirty” image and the fact that it is non-renewable (Gonzalez-Salazara et al., 2018). It triggers the rapid development of a coal-fired power plant’s technology, increasing efficiency and reducing environmental impact (Fu et al., 2015). In a competitive and uncertain market, the main factors considered for the survival of a power plant are energy, economic, social, and environmental issues (Petrillo et al., 2016; Luo et al., 2020). Certain problems need to be handled appropriately. First is the way and manner to manage the efficiency and reliability of the power plant while maintaining a safe environmental impact during the operating period, under certain government regulations. Normally, a life cycle management (LCM) plan addresses all of these issues. Formal definition of life cycle management is an integration of operation, maintenance, engineering, and business activities to manage asset condition, optimize asset life, and maximize asset return on investment. The two main elements of asset management are physical and financial asset management (Figure 1). Physical asset management is used to improve and maintain the asset condition through implementing efficiency and reliability management. Financial asset management is used to maximize asset value by reducing costs and increasing revenues.
Figure 1 LCM Concept
The first LCM framework was initially developed and implemented in a
nuclear power plant (EPRI, 1998). In
addition, it is known as Nuclear Asset Management (NAM). The LCM framework
focuses on reliability improvement (Sliter and
George, 2003; Raghawan and Chowdhury, 2012). Several preliminary studies
reported that reliability does not consider the power plant's efficiency (Singh and Jaswal, 2013; Pariaman et al., 2017; Melani et
al., 2018). Similarly, most studies carried out in ways that increase
efficiency do not take into account reliability. Furthermore, there are five
factors that affect the coal-based power plant's efficiency. The first factor
is design choices (Li et al., 2010; Stover et al.,
2011), second is fuel strategies (Xia et
al., 2014; Xu et al., 2016), third is operational practices (Xiong et al., 2012; Hübela et al., 2017), fourth
is pollutant control (Munir et al., 2011),
and fifth is ambient conditions (Zhang, 2015; Petrescu
et al., 2017). None of the aforementioned studies analyzed both
efficiency and reliability. Secondly, the power plant needs to simultaneously
pay attention to sustaining its revenue. This depends on uncontrollable
external factors, such as electricity demand and competitors or the market's
behavior. This has become a significant challenge in the Volatility,
Uncertainty, Complexity, Ambiguity (VUCA) era. The COVID-19 pandemic has
significantly reduced electricity demand worldwide (Elavarasan
et al., 2020). This led to a change in customers' behavior, because most
people prefer to work from home. In addition, there was an increase in
residential load. In contrast, the commercial and industrial ones decreased due
to the slackening of business activities as an attempt to minimize the spread
of the virus (Berawi et al., 2020). However,
the decline in demand causes a decrease in the capacity factor (CF) of the
power plant. In Indonesia, the projected CF was reported as 28.33% between 2020
and 2024 compared to 54.96% recorded in 2019, due to oversupply and COVID-19
impact (PLN, 2020). With a 47.7% reserve
margin, as a consequence, several power plants have to temporarily standby or
permanently shut down. This also affected the expected revenue from the initial
project. Therefore, there was a need to ascertain whether the power plant was
continuously operated, rehabilitated, or demolished. The objective was to
either maintain the targeted financial performance or at least minimize the
losses. This led to the final problems related to ways to optimize and detect
the economic life of an asset. According to asset management standard (ISO 55010, 2019), the optimum time for
investment intervention is the point when the overall life cycle cost of an
asset is minimal (Figure 2a). In the power generation sector, this approach is
established in a framework named integrated life cycle management (ILCM), as
the development of LCM (Esselman et al., 2012).
This focuses on the equipment or component level and ways to minimize its cost.
Early replacement makes a higher total cost because the probability of failure
is still relatively low compare to investment cost (zone 1). But replacement
too late also makes it higher due to higher force outage cost (zone 2).
Integrated life cycle management could not analyze the system or power plant
level because it does not consider the revenue, while the plant has to consider
both cost and revenue. The cost is dominant from internal factors and
controllable by the power plant. On the contrary, revenue is more dominant from
external factors and uncontrollable. Incentives on feed-in tariffs or tax
credits could improve its overall cost competitiveness and make it more viable (Yang et al., 2021). In the grid system, the plant
configuration has a significant impact, economically and environmentally (Destyanto et al., 2017; Xu et al., 2017; Njoku et al.,
2020). Based on the references above, there is a significant gap in the
studies that separately investigated efficiency, reliability, and optimum
replacement analysis. None of the studies analyzed a combination of efficiency
and reliability, its impact on cost and revenue, or the ways to optimize an asset
life cycle at the power plant level (Wibawa et al.,
2019). This led to the introduction of a novel approach called the
Holistic Operation and Maintenance Excellent (HOME). This approach is based on
the combination of efficiency, reliability, and replacement analysis to
optimize the asset's life cycle. Furthermore, it also combines the cost and
revenue of the power plant. This approach significantly analyses all the
factors associated with the VUCA era. Subsequently, this research is organized as
follows: first is the concepts and methodology, followed by its implementation
in the power plant (industrial case study), and finally, analysis, discussions,
and conclusions to determine whether or not it is suitable to address all these
problems.
The proposed HOME
concept has been proved to fulfil the gap of the previous LCM framework. It comprehensively combines
all of the technical and financial analyses needed to support the decisions of
the power plant owner, whether it needs to be kept, rejuvenated, or demolished
for good. A combined analysis of
efficiency and reliability is realized through any change in fuel, operation,
or maintenance strategies. The impact on cost and revenue tends to be
simultaneously analyzed. The case of fuel changing strategies (HRC and LRC),
studied and reported in this research, shows that the HOME frameworks are
proven to aid in deciding what to do with the power plant under investigation.
It is also capable of predicting the future impact of the external factors on
the revenue. The optimum decision concerning whether the power plant needs to
be continuously operated, rejuvenated, or demolished, has to be analyzed. The HOME
project aids the power plants in simulating and predicting the possibility of
all strategic options during its operational period. In addition, the power
plant also needs to avoid unnecessary maintenance or rejuvenation, or
rehabilitation activities by taking the appropriate decision towards the end of
its life cycle. The implementation of the advanced and future power plant
technology is easily evaluated and justified. In the case study analyzed in
this paper, if it only takes into consideration reliability and efficiency, the
power plant under investigation will have to use HRC. The higher the calorific
value, the higher its reliability and efficiency. Unfortunately, as it has been
simulated and analyzed, those two factors are not enough to justify the
viability of the coal calorific values to be used. The other factor that has to
consider is the total cost. The total cost will impact the minimum CF to reach
the break-even point (CFBEP). Combining those three factors
(reliability, efficiency, and CFBEP) into the analysis as suggested
by the HOME framework, provides the best decision for all aspects of the power
plant, such as operation maintenance, cost, and revenue. Based on Table 5, HRC
and LRC could be used if the power plant has a CFPRED of 79.46%. The
efficiency and reliability would decrease and generate more carbon emission
when using LRC. It needs more expensive maintenance, but produces more profit
than HRC. If the CFPRED reduces to 60.96%, then only the LRC is
viable. Rehabilitation or rejuvenation must occur when using LRC. Based on the
case study, the HOME framework was extremely effective and used to make the
best decision concerning the power plant under investigation. This is necessary
in order to remain competitive in an uncertain electricity market and business
condition. It effectively guides the power plant operation and maintenance by
providing the best decision at every stage (age). However, integrating and
directly linking it to the power plant database, such as the DCS and the CMMS
for operational and maintenance data, provides a dynamic and simultaneous
analysis of the current position of the performance and prediction. This saves
a lot of time and money and ensures the power plant is always a competitive
edge in terms of the cost of electricity generated and, even more important, in
the current VUCA condition. In this case study, the acquisition cost is
constant. On the contrary, the disposal cost is negligible. In certain
circumstances, such as asset reevaluation or divestment, the acquisition and
disposal costs were very important to consider. It has a significant impact on
the total cost and parameters that to consider for future research.
Data
support for this research was provided by PT PJB, as a subsidiary of PT PLN
(Indonesia’s state electric company) and the authors gratefully acknowledged
them.
Filename | Description |
---|---|
R2-ME-4827-20210613180942.docx | Research DataFile |
Barros, J.J.C., Coira, M.L., de la Cruz Lopes, M.P., del Cano
Gochi, A., 2016. Probabilistic Life Cycle Cost Analysis for Renewable and
Non-Renewable Power Plant. Energy, Volume
112, pp. 774–787
Berawi, M.A., Suwartha, N., Kusrini, E., Yuwono, A.H.,
Harwahyu, R., Setiawan, E.A., Yatmo, Y.A., Atmodiwirjo,
P., Zagloel, Y.T., Suryanegara, M., Putra, N., Budiyanto,
M.A., Whulanza, Y., 2020. Tackling
the COVID-19 Pandemic: Managing the Cause, Spread, and Impact. International Journal of Technology. Volume
11(2), pp. 209–214
Destyanto, A.R., Hidayatno, A., Amalia, A., 2017. Analysis of The
Effects of CO2 Emissions from Coal-Fired Power Plants on the Gross
Domestic Regional Product in Jakarta. International Journal of Technology,
Volume 8(7), pp. 1345–1355
Electric Power Research Institute (EPRI), 1998. Nuclear Plant Life
Cycle Management Implementation Guide. EPRI Report 106109, Palo Alto, CA
Esselman, T., Bruck, P., Menger, C., 2012. Integrated Life Cycle
Management: A Strategy for Plants to Extend Operating Lifetimes Safely with
High Operational Reliability. IAEA,
CN-194-034, pp. 1–8
Fu,
C., Anantharaman, R., Jordal, K., Gundersen, T., 2015. Thermal Efficiency of
Coal-Fired Power Plant: from Theoretical to Practical Assessment. Energy Conversion and Management, Volume
105, pp. 530–544
Gonzalez-Salazara, M.A., Kirstena, T., Prchlik, L., 2018. Review of
the Operational Flexibility and Emissions of Gas and Coal-Fired Power Plants in
a Future with Growing Renewables. Renewable
and Sustainable Energy Reviews, Volume 82(1), pp. 1497–1513
Hübela, M., Meinked, S., Andrénb, M.T., Wedding, C., Nockea, J., Gierowa,
C., Hassela, E., Funkquist, J., 2017. Modelling and Simulation of a Coal-Fired
Power Plant for Start-Up Optimization. Applied
Energy, Volume 208, pp. 319–331
International Energy Agency (IAE), 2017. World Energy Outlook
International Organisation for Standardization, 2010. Guidance on the
Alignment of Financial and Non-Financial Function in Asset Management. ISO/TS 55010:2019(E)
Li, M., Rao, A.D., Brouwer, J., Samuelsen, G.S., 2010. Design of
Highly Efficient Coal-Based Integrated Gasification Fuel Cell Power Plants. Journal
Power of Sources, Volume 195, pp. 5707–5718
Luo X.J., Oyedele, L.O., Owolabi, H.A., Bilal, M., Ajayi, A.O., Akinade,
O.O., 2020. Life Cycle Assessment Approach for Renewable Multi-Energy System: A
Comprehensive Analysis. Energy Conversion
and Management, Volume 224,
https://doi.org/10.1016/j.enconman.2020.113354
McNerney, J., Trancik, J.E., Farmer, J.D., 2011. Historical Cost of
Coal Fired Electricity and Implications for the Future. Energy Policy, Volume 39(6), pp. 3042–3054
Melani,
A.H.A., Murad, C.A., Netto, A.C., de Souza, G.F.M., Nabeta, S.I., 2018.
Criticality-Based Maintenance of a Coal-Fired Power Plant. Energy, Volume 147, pp. 767–781
Munir, S., Nimmo, W., Gibbs, B.M., 2011. The Effect of Air Staged,
Co-Combustion of Pulverized Coal and Biomass Blends on NOx Emissions
and Combustion Efficiency. Fuel, Volume
90(1), pp. 126–135
Njoku, I.H., Oko, C.O.C., Ofodu, J.C., Diemuodeke, O.E., 2020. Optimal Thermal Power Plant Selection for
a Tropical Region using Multi-Criteria Decision Analysis. Applied Thermal Engineering, Volume 179, https://doi.org/10.1016/j.applthermaleng.2020.115706
Pariaman, H., Garniwa, I., Surjandari, I., Sugiarto, B., 2017.
Availability Analysis of the Integrated Maintenance Technique based on
Reliability, Risk, and Condition in Power Plants. International Journal of Technology, Volume 8(3), pp. 497–507
Petrescu, L., Bonalumi, D., Valenti, G., Cormos, A-M., Cormos, C-C.,
2017. Life Cycle Assessment for Supercritical Pulverized Coal Power Plants with
Post-Combustion Carbon Capture and Storage. Journal
of Cleaner Production, Volume 157, pp. 10–21
Petrillo, A., De Felice, F., Jannelli, E., Autorino, C., Minutillo, M.,
Lavadera, A.L., 2016.
Life Cycle Assessment (LCA) and Life Cycle Cost (LCC) Analysis Model for a
Stand-Alone Hybrid Renewable Energy System, Renewable
Energy, Volume 95, pp. 337–355
Elavarasan, R.M., Shafiullah, G., Raju, K., Mudgal, V., Arif, M.T.,
Jamal, T., Subramaniang, S., Balaguru, V.S.S., Reddy, K.S., Subramaniam, U.,
2020. COVID-19: Impact Analysis and Recommendations for Power Sector Operation.
Applied Energy, Volume 279, https://doi.org/10.1016/j.apenergy.2020.115739
Singh J., Jaswal, R.A., 2013. Evaluation of Reliability Parameter
of the Thermal Power Plant by BFT. International
Journal of Advanced Engineering Technology, pp. 79–81
Sliter, George, E., 2003. Life Cycle Management in the US Nuclear
Power Industry. In: Transactions
of the 17th International Conference on Structural Mechanics in
Reactor Technology (SMiRT 17), Prague, Czech Republic, August 17 –22,
pp. 1–8
Raghawan, S., Chowdhury, B., 2012. Developing Life Cycle Management
Plant for Power Plant Components. In: Conference North American Power Symposium (NAPS)
State Electric Company (PT. PLN), 2020. Electric Power Supply
Plan for Java-Bali System (RPTL) in 2021-2025
Stover, B., Bergins, C., Klebes, J., 2011. Optimized Post
Combustion Carbon Capturing on Coal Fired Power Plants. Energy Procedia, Volume
4, pp. 1637–1643
Wibawa, A., Ichsani, D., NurYuniarto, M., 2019. Power Plant Life
Cycle Cost Management Framework: A Literature Review. Journal of Physics Conference Series, Volume 1485, pp. 1–9
Xia, J., Chen, G., Tan, P., Zhang, C., 2014. An Online Case-Based
Reasoning System for Coal Blends Combustion Optimization of the Thermal Power
Plant. Electrical Power and Energy System,
Volume 62, pp. 299–331
Xiong, J., Zhao, H., Zhang, C., Zheng, C., Luh, P.B., 2012. Thermoeconomic Operation
Optimization of a Coal-Fired Power Plant. Energy, Volume 42(1), pp. 486–496
Xu, C., Xu, G., Zhao, S., Dong, W., Zhou, L., Yang, Y., 2016. A
Theoretical Investigation of Energy Efficiency Improvement by Coal Pre-Drying
in Coal-Fired Power Plant. Energy
Conversion and Management, Volume 122, pp. 580–588
Xu, J., Gu, J., Chen, D., Li, Q., 2017. Data Mining-Based
Plant-Level Load Dispatching Strategy for the Coal-Fired Power Plant
Coal-Saving: A Case Study. Applied
Thermal Engineering, Volume 119, pp. 553–559
Yang, B.,
Wei,
Y-M., Liu, L-C., Hou,
Y-B., Zhang,
K., Yang, L., Feng, Y., 2021. Life Cycle Cost Assessment of Biomass Co-Firing Power
Plants with CO2 Capture and Storage Considering Multiple Incentives.
Energy Economics, Volume 96, https://doi.org/10.1016/j.eneco.2021.105173
Zhang, C., 2015. A Software for Optimizing the
Thermal Power Plant Operation Under Environmental Constraints. In: Proceedings of the 4th
International Conference on Mechatronics, Materials, Chemistry and Computer
Engineering 2015, pp. 2815–2818